Sunday, January 12, 2014

Good things come in threes...

There are certain topics that I've historically given a wide berth to. Project governance is one of them. It's too easy a target, too contentious and every one has an opinion on the matter. Here's mine.

One of the things that's constrained having any sort of consistent dialogue / vehicle / entry point (delete as appropriate) via which governance is (or ever could be) dealt with in projects (and programmes) is the lack of a unified consensus.

Well, you ask, what does that mean? Good question. If you asked 10 project managers what do they understand to be implicit in the term project governance you will (I hazard) elicit a variance in the responses that is extremely difficult to unify. You could even swim into less certain waters still by asking "What are the hallmarks of a well governed project by comparison to a poorly governed project". Could anyone be confident of any kind of spontaneous consensus?

The splenetic Steve Jenner (who will I hope overlook any referencing of his words in deference to my describing him as splenetic) offered that "...governance is the job of defining what decisions are made, by whom, when and to what criteria...". I remember feeling a sense of overwhelming gratitude to Steve for having (I felt) pinned the tail onto the donkey quite so precisely, succinctly and without apparent contentiousness.

But then, you've also got corporate governance, IT governance, data governance and quite a bit more besides.

...and that's just the different areas of governance. There are different approaches to governance such as collaborative or multi-stakeholder. And then of course there's applying both the required area of governance (say Project Governance) to (say) an IT Project in (for instance) a multi-organisational project. Oh, and just in case that wasn't enough - how about meta-governance - the governing of governance. (I do yearn for a bit of this now and again mind you).

Incidentally - just in case you were about to yawn and look for your entertainment elsewhere since this wasn't a terribly interesting topic, consider for a minute a project in which the wrong decisions are made, by the wrong people, at the wrong time and to the wrong criteria. Does this sound a bit more engaging now?

Like any project manager faced with unmanageable levels of complexity I revert to the mental state of a 3 year old, effect a brief but meaningful inner tantrum and cling to the mantra - surely there is a simple way of ensuring that tomorrow is better than today.

...and of course, there is.

Simple step one to improving governance today

Documented process is an enabler (dependency?) for improving governance. So, in the very simple situation below we have an input, a decision and two possible outcomes. We have a decision point, some inputs (criteria) and presumably a forum or framework in which that decision will be made. Sounds a bit like we're half-way to something Steve Jenner might just suffer to include under the heading of governance.




Simple step two to improving governance today

Create a register of all the formal documentation to be produced during the course of your project / programme. Include information about who is going to produce it, who is going to review it, who is going to sign if off and who is going to own it going forward. And, any schedule information for when this documentation will be created. Publish this register to appropriate stakeholders (and in many instances this will simply be all of them).

This resource, at a glance, allows a range of stakeholders to discern what documentation is to be produced (and what documentation isn't), by whom, when and who is (and isn't) involved in review and sign-off.

Simple step three to improving governance today

Create and publish a product breakdown structure (PBS). Derive from this appropriately detailed product descriptions and keep these someplace useful (say a product dictionary - a.k.a. an Excel worksheet. This is very much the same carry on for step two (which applies specifically to documentation) but in this case we're looking at specific project deliverables (which may or may not be documents).

This resource, at a glance, allows a range of stakeholders to discern what products are to be produced (and what products aren't), by whom, when and who is (and isn't) involved in review and sign-off.

And that will do won't it? No expensive management consultants. No particular undue stresses and strains. Not even a requirement for the oversight of assurance satsumas mandarins - just a bit of practical elbow grease.





Monday, December 30, 2013

Problems with unrealistic objectives

A while back I wrote a post entitled "Fail less with project management" I remain broadly happy with the sentiments I expressed. Perhaps the most succinct summary I can relay is via the metaphor of an aircraft flight in which a plane, encountering stronger headwinds than expected, will burn a bit more fuel and take a bit more time. It will however ultimately touchdown safely at its intended destination. A success in aviation terms. Not quite such a clear cut case in project delivery terms.

I only found out recently that the Association for Project Management has a vision of "...a world in which all projects succeed".

Does this mean that collectively we cease to embark upon projects that are deemed risky? Does this mean that project managers who do not succeed in delivering projects have failed?

And now for a bit of multi-choice.

There is often a tension between two competing imperatives for the project manager. The delivery of a successful project and the successful delivery of the client's strategy. As an experienced and seasoned project manager is it your job to;
  1. Deliver a successful project whether or not it is the strategy of your client
  2. Deliver the strategy of your client whether or not it results in project success
  3. Neither option
For me and my blog, the answer is option 2. In a client facing scenario, what I'm actually going to say is that as a professional change practitioner my job (and that of the team) is to reduce risk, add value and accelerate delivery. 

For those of you who went  for option 1 - best of luck - I recommend you keep the phone number of your professional indemnity provider handy.

For those of you who went for option 3 - with some sort of managed approach to influencing the sponsor away from his or her chosen strategy (assuming you have good reason for doing so) I would offer the following. First, the most effective way to do this may well be to fail quickly and conspicuously in any attempt to deliver it. Secondly and more importantly, as an "experienced and seasoned project manager" that isn't your job. Is it? (If you can't live with this, fear not. A successful career in project assurance may be beckoning).

But I said 'problems' with unrealistic objectives. Not 'problem'. Personally (though it may yet limit my career) I don't have any problems in telling the client that we've burnt a bit more fuel and we're going to take a bit more time because the headwinds we encountered were a little greater than we forecast 6 (12, 18, 24+?) months ago. One of the reasons I don't mind is that my job is to add value, reduce risk and accelerate delivery first and to deliver successful projects second.

If you don't adopt this sort of credo, you might find yourself overusing words like "contextualised success", "positioning" or possibly even "the war situation has developed not necessarily to Japan’s advantage".
 
So, if your client has opted for an approach to change that you're not altogether convinced about, I'd recommend helping the client develop the necessary information assets as quickly and cheaply as possible so that you can back-up, rethink, re-plan and take a second swing at it.

Other views undoubtedly exist.





Saturday, October 19, 2013

This is not a post about critical chain project management

Ever had an itch you can't scratch? I don't have one of those.

What I do have is a lingering doubt. A sense that something or someone could answer a lot of questions if I just knew the right questions to ask and the right forum in which to ask them.

Some of these doubts and uncertainties have been discussed previously in this blog. But for clarity I'm going to cite the half dozen things that (I think) are just not good enough in project management right now.
  1. Planning. Consistently falls short of what is required. Work is not identified, not adequately defined, not forecast accurately and doesn't have the corresponding supporting information to enable the brokering of appropriate resources. Successors and predecessors aren't pinned down accurately, F-S, F-F, S-F relationships aren't identified with the precision required
  2. Resource brokering. If (as is the case within technology infrastructure projects) your project's delivery is dependent on skilled and scarce human resources  then resource brokering should be fit for purpose. Hands up all those people who work on projects with great resource brokering.
  3. Success. Don't get me started (mainly because there's an angry man here who already has)
  4. Perception. Does anyone out there hold projects, project teams, project managers in high esteem?
  5. Benefits / return on investment. Goodness me but there are far to many people charging out for delivering change when surely the game should be delivering benefits.
  6. Profits. Executing change effectively and efficiently will enable you to deliver your strategy with less risk and more value than your competitors. It follows that your costs will be lest, your agility greater and your profits will reflect this. 
Notwithstanding all this, there's Prince 2 and PMP accreditations, quite a bit of software intended to solve some of the knottier project management headaches, a recognition that practitioners of change are specialists and even that some expenditure on those specialists is a worthwhile investment. And, health checks, specialist consultancies, more historical data than you can shake a stick at, more than one MSc and a partridge in a pear tree. 

Perhaps most importantly (and I can speak a bit from experience here) there's quite a few bright folks in the industry and there is no limit to their determination and tenacity in trying to bring projects in on time (whatever on time means - 'cos I'm starting to get a bit jaded around that - but more on the "Aggressive but Possible" (ABM) vs. "Highly Probable" (HP) paradox another time. Discussions of 'on-time' aside, there's still the questions of scope, quality, benefits and cost.

Could it be there's something fundamentally wrong with the underlying mechanisms of project management or their application? I could go the route here of an extended negative hypothesis routine in which we discounted one by one all the other candidate explanations. I'm reasonably certain that a blog post is neither the time or the place. So let's cut to the main course.

Planning assumption #1 then; there's something wrong with project management approaches / mechanisms. Or at the very least something wrong with the way they're applied. 

If this planning assumption is born out (and there's quite a weight of evidence to suggest that it might be) then ideally we'd need something waiting in the wings as a substitute. While the current status quo is (ripe?) for improvement, it wouldn't be impossible to make it worse.

And that substitute just might be Critical Chain Project Management. I'm not going to tell you what I think. There would be an implication perhaps that you too should be thinking that. I think we all need to come to our own independent conclusions about Critical Chain Project Management but I will post on it again in the future and if it elicits only critical scrutiny of existing methods and approaches then that alone will be a worthy objective.


Sunday, September 29, 2013

A cow, an Alderney and a raging bull...

Apologies for the gratuitous blog title. Google's decision to withdraw their excellent Reader tool has quite scythed my readership statistics with a corresponding impact to my moral.

I'm minded to start up such cheap tactics as including the names of minor celebrities such as Paris Hilton and Miley Cyrus simply to catch some incidental drive by traffic.

As a jobbing project manager, one of course does get a reasonable level of exposure to the catalogue of general (and often dubious) apocrypha that accompanies the day to day cut and thrust of managing change.

An example of such apocrypha would be "...all projects succeed and all projects fail. Just to varying degrees of both..." which is possibly a little trite, but I quite like it all the same.

One such example which I don't like is "...you pay a project manager to worry so you don't have to...". I've never liked this terribly much because in theory a very talented worrier is suddenly a sought after commodity and I'm not one of those.

And then there's this little gem "...you pay a project manager to communicate..". Simple, undisputed fact. I like it.

Perhaps because I'm a little left of centre about these things, I've always thought that Alex Alexander Milne's "The King's Breakfast" contains many allegories useful for the project manager. There's some stakeholder management, some requirements management, setting of expectations and supplier management all in a few simple lines intended to amuse children. There's even some remarkable insights into value management. (Okay - that last one is a bit of stretch

So perhaps now is an opportune time to elaborate a little on the title of this post. One of the challenges faced by the PM is summoning the language, the agility, wit, poise and timing to communicate effectively. Don't get me wrong, the PM isn't unique in having these challenges but the PM is certainly likely to be in the room when;

  1. The sponsor asks for dairy products from the cow;
  2. The supplier questions whether it is an Alderney or a Friesian from which the afore mentioned dairy products should be derived and;
  3. The site foreman explains that no amount of coaxing is going to persuade an angry bull to give up a pint of the white stuff.
Yes, yes - I know, all part of the usual carry on a project management. But for our purposes here, we're talking about milk, Friesian's and bulls. And, you won't be. You'll be talking about change and, likely as not changes to an existing landscape many years in the making. You won't be talking to the king, the queen and the dairymaid, you'll be talking to real people with real skin in the game each of which is likely to have different needs and agendas, some of which will undoubtedly conflict. The information they want will be put to different purposes and will need to be presented in a range of different formats and mediums. Sometimes it's a one off and sometimes it'll be a repeating and up-to-date feed potentially updated in real time.

If this isn't delivered or can't be delivered it's likely to be the PM's phone that starts ringing.

So what useful steps can taken up front to guard against the prospect that either you can't or don't communicate as required. And, to understand the expectations and, where necessary to inform them.

  1. Process and procedure. I'm not going to labour this one, I hope rather that it is self-evident. If you don't have process and procedures, make sure you can report on whatever alternative is in place. And by the way, I'm not altogether sure what that alternative is Semantics aside, there's usually a way to navigate around aspects of work that are inherently not susceptible to process. Wrap process and reporting around them and 'go up the stack' to ensure that the entry and exit points are understood within an overarching 'flow of process'. Acknowledge that there may be elements of the overall flow of process which are able to be more accurately and more precisely reported upon than others.
  2. Validation and verification. Make sure you're doing the right thing. And make sure that thing is done right.
  3. Nomenclature and language. Make sure that you're all singing from the same hymn sheet. Make sure your inputs are capable of supporting the required reporting outputs. Do not make assumptions that the data will just join up. Define it to the required level of detail and perform the requisite static testing and prototyping to ensure that it all stacks up.
  4. Create standards, generate and publish a configuration management policy which is aligned and supports your overall reporting aims.
  5. And perhaps most importantly make sure you, as PM ,are in the room to inform the discussions to make sure these steps are taken and that the necessary resources are allocated to the tasks.
 So, as it turns out, the phrase  "...you pay a project manager to worry so you don't have to..." might not be so much dubious apocrypha but rather something to say three times a day before you go to work to ensure that not for one minute do you ever forget it.














Saturday, June 1, 2013

People are objects with attributes too.

Statements like "...soft skills are an essential and often overlooked aspect of project management..." and "...the importance of getting the right people for your project team cannot be understated..." are the sorts of thing that make me want to swear off the canon of generalist project management literature for good.

Not, you understand, because it's not true. But, because it's self evident and this sort of nonsense makes the job of project management look like the job of professionalising common sense.

I was addressed by a senior member of public sector management some years ago who offered (and I paraphrase here) that "... in the 1990's we hired people for their skills, in the 2000's we hired people for their knowledge and in the 2010's we'll hire people for their behaviour." I hope this worked out okay for those people adopting such an approach.

Quite how you hire someone (or even assess someone in interview objectively) on the basis their behaviour I'm unsure. For all I know, it might not even be lawful.

I do remember thinking at the time that I would continue to hire people on the basis of their talents, track record and ability. I offer it's served me satisfactorily in almost all instances. And, as often as not, supremely well.

Whatever organisational hiring framework you're faced with (challenged by...?), you can adopt and overlay the following approach to determine what you need and help you go and get it.

Someone may offer something supplemental to this appraisal but for the purposes of employment I seek to assess initially what I need someone to know, what I need someone to do and what I need someone to be. Hence the term, "know, do, be framework".

For, let us say, a prospective defect co-ordinator we might define the following know do be framework. I've made the file accessible here if anyone's interested.




So we've taken something somewhat nebulous and intangible, put some structure around it and quantified it. This is I hope well understood to be my general preference for most things. I don't know about you, but I'm already feeling a lot happier about my ability to define and articulate what it is I want.

If you're lucky, you'll be solely responsible for the hiring and you can now formulate some interview questions (or other assessment) via which you can assess a candidates alignment with the know, do, be framework.

Even if you're simply a passive invitee to an interview you can assess a candidate's suitability against your identified criteria and express your preferences accordingly. 

One other point worth noting. You can reverse engineer most job descriptions with this approach. Pick out the key requirements and define some key points in line with what you know, what you are, and what you do that support those requirements. This can be very helpful if you're filling an application form (who still uses those?) but can perhaps more usefully equip you with some very strong responses to likely interview questions.


Sunday, May 12, 2013

WBS - Second Foundation

A previous post (WBS as foundation) is far and away the most read post on my blog. So (and with a passing reference to Mr. Azimov) I'm following up with some additional practical tips that I use on more or less a daily basis.

For what a WBS is, how to construct one, what its ideally applied to and its limitations see my previous post.

So we still use the hierarchical structure previously described and I tend to use the SmartArt feature in Excel to generate and maintain the WBS structures. I tend to keep things fairly segmented - one worksheet per WBS and one WBS per work stream.

Please, please note - there are some big powerful tools out there for generating and maintaining WBSs. SmartArt works for me because as often as not I'm in a position to decompose stuff to a level that suits me. It may not work for you.

What I do next is create a product dictionary on a separate worksheet. I'll include a sample spreadsheet in a little while so you'll see the whole shooting match in action. There's a reason we put all the products on one sheet and you'll see that in the template I supply.

I cite a few points worth consideration.

  1. In my last post I talked about the constant K - and idealised abstraction of the total amount of work required to deliver your project assuming no waste. This is relevant to our discussion here as K1 is the volume of work not identified during planning and due diligence. If you can't include it at the outset of a project, include the work as you discover it within the WBS and product dictionary - there's all sort of good reasons why.
  2. The product dictionary is a fantastic way of tracking all your discrete components of work, who's doing it, the status of the work and a host of other stuff to
  3. The work breakdown structure and the product dictionary comprise a very good record of the work done, work in progress and work yet to be started.
  4. The product dictionary forces a degree of rigour into the definition of work that is issued to members of the project team
  5. If you do define the WBS and product descriptions up front, the project plan will pretty much write itself. I succeed in winning this argument about 50% of the time and that 50% is always a better oiled and tuned project than the other 50%.
  6. Both the WBS and product descriptions can form a very useful foundation to reporting and communication (what's done, what remains to be done and so on).
So there's a lot to recommend these two products and we can still extract a bit more smartness from the approach. See my work book here. I've included two different WBSs, each of which applies to a different work stream. We've got a product dictionary with a number of products assigned to three different people. There's a bit of filtering applied which means we can (for instance) pull all the products assigned to a given individual. And there's a bit of conditional formatting which means the individual line items change colour depending on their status which makes keeping an eye on things that little bit easier.

You could configure conditional formatting to change the colour (say) for items that are 7 days before their due date or for items that are due or overdue. But, that's really something I tend to rely on my project plan for.

You'll notice a lot of duplication in the sheet. In the instance here this is because this is a specimen created solely for you delectation and delight. However, it does highlight a particularly useful element of working in this fashion which is within any product dictionary there is a great deal of duplication. The Quality Criteria are generally re-usable for various products as are the resources and acceptance method. In short, these build nice and quickly, particularly where there's a bit of existing policy, process and procedure which can be referenced.

Lastly - something useful in Excel is the paste special 'transpose' function which means I can take any row, paste special and transpose into the 'product description' sheet as shown and I've a readily communicable summary of the product description to do with as I wish. If the product description looked familiar - it's a standard Prince 2 product.

And that is really about all there is to it.

Sunday, April 14, 2013

Late for a very important date - again?

Say what you will, most projects don't get delivered on time. A critical appraisal might include the word late. I'm starting to think however that the terms 'on time' and 'late' are worth consideration. And maybe, if enough consideration is given to the subject perhaps there might be something genuinely novel and interesting to conclude about the nature of projects generally, the frailty of current management approaches and what can be done about it.

There's an interesting blog post here that I read sometime ago - you should read it but in absolute summary - there's no such thing as slipping dates, just bad forecasts. I remember this really making an impression with me when I read it. I don't just think its a good point, I think its a potent entry point to a much richer discussion.

A while back I prattled on about an idealised constant 'K', which represented all the work that was required to be done to complete your project assuming no waste. I've re-rendered the drawing below.



There's some simplification here. There's no discussion of change requests, procedural acumen or PMO statistics for this sort of project run in your organisation but broadly;

Work that needs to be done to complete your project is K
Work that you identify to be undertaken for your project is Kb
Magnitude of error in plans is K - (k2) + (k1).

k2 is interesting as you may or may not end up doing it and to some extent it cancels out k1 which you'll always have to do.

What's our list of variables then? Things that might influence k1 & k2. I suggest the following
  1. Preliminary planning fails to identify accurate the work that needs to be undertaken or the time it will take to complete it.
  2. Failure to accurately identify dependency relationships, leads and lags
  3. Blunders, poor forecasting and re-work
  4. A change budget (£/$) but no corresponding schedule allowance
  5. HR Management issues (absence, incompetence and ineptitude)
  6. Failure to manage complexity
  7. Criminal or unlawful activity
  8. Acts of nature
Of the 8 points above, I would suggest that item 1 is far and away the most significant. Some other time I might take the time to blog on the predilection of homo sapiens to focus on outliers at the same time as dismissing the significant but for the time-being I think I'll simply focus on items 1, 2 & 3 above.

Let's take a moment to summarise and take stock. Project delivery consistently moves to the right (perhaps systematically so) and there is (I suggest) some consistent harbingers of this movement. Interesting this isn't it? We've got a consistent output (delays and destabilisation of the project schedule), consistent inputs (I'll continue to subscribe to points 1-3 above - other views almost certainly exist). Shouldn't this mean we can do something to quantify and assess the potential impact to our projects?

There's a little bit of overlap here potentially with the schedule performance index which I mention here. But its not quite the same animal. Firstly, you've actually got to implement some rudimentary earned value management and (somewhat shockingly) almost no one ever does. But it will only help you so much as it will only use a sample of work done so far rather than a more useful measure the project in its entirety. This means you'll get increasingly good data as your project progresses but at the outset, it'll be highly unreliable.

At this point, I feel I want to talk about cooking for a while. 

Cookbooks are full of recipes. They describe the ingredients and implements required, the steps, temperatures and techniques to use and usually describe the output. They do this consistently well otherwise people wouldn't buy them.

If you follow the instructions and you have a little culinary acumen you can have a high level of confidence that what is delivered will be edible. Delicious even. If however, you use second rate ingredients, rush the prep, burn the food and respond to a late request to remove the anchovies, there's significantly less chance that what you deliver will be fit for purpose or on time.

Cookbooks are a good illustration of our idealised constant 'K' that I mentioned above. They do have the advantage however that a) they're not a unique undertaking and b) almost universally they'll have been reworked and rehearsed perhaps over several generations. So, they're not projects are they. But they do highlight the importance of knowing everything there is to know at the outset and what the benefits of knowing everything are.

Continuing on our epicurean line for a spell longer. If we removed some of the ingredients and steps from a recipe we'd be doing something to model in abstract the deficiencies in planning to which many projects (all?) find themselves prone. Would we be able to identify the omissions? What could we do with them if we did identify them?

We'll, there's one sure way of identifying that there are omissions (as opposed to what they are) and that's cook the dish. I don't think its too much of a stretch to suggest that any omissions could be identified and quantified. So what's the benefit of investing this time and effort? What can we do with the information we're now in possession of?

Can we extrapolate anything about the remainder of recipes in the cookbook (project)? Can we play any discrepancies across the remainder of the project? Well, maybe. Omissions from the fish section might not be applicable to the dessert section and should you take your cookbook to your aunt's for Sunday roast, all bets might be off when comparisons are made with cooking in your own kitchen. This is where the schedule performance index (and cost performance index) fall short for our purpose here - they focus exclusively on the sample of work that has been done, not a proportionate sample of the whole piece.

What I am tilting at here is that if we cook a few recipes up front we'll be better able to assess the cookbook in its entirety. The more recipes we test (the greater the sampling) the better picture we'll develop of the overall scheduling, scope and procedural quality.

So what next? I'll seek to elaborate the points above and answer the following questions.


  1. When is this sort of critical appraisal essential as opposed to desirable or superfluous?
  2. What could the job of analysis of a project scope / schedule entail?
  3. What could the output be used for?
  4. Who would do it? When? And for what purpose?





Sunday, March 3, 2013

Forecasting - part four

Ironically in my first post on forecasting I cited the following points which I would aim to cover.
  1. Parametric or reference class forecasting
  2. Guessing, uncertainty and pragmatism
  3. Never mind 6 Sigma - 1 will do you quite nicely
  4. The PM's job in fighting for exactitude and rigour in the planning process
  5. Some helpful language and strategies to challenge sub-standard practice
  6. Some real life scenarios and tools consistent with other articles in this blog that I hope will add a bit of value
And here we are on the fourth post on the topic and I think I still have pretty much the lot still to get through. Something relevant to the topic of forecasting in their somewhere methinks.

Let's hustle on a bit. 

Parametric or reference case forecasting is simply the process of using historical events to inform forecasting. Let's go back to our example of changing a car tyre. I discussed some useful stratagems on getting to a more accurate forecast, but ultimately you can't beat having changed a tyre yesterday to inform a useful forecast on how long it might take today.

Guessing? Don't do it. If you don't know how long something is going to take, set a duration on your project plan and commit to using a schedule performance index to track progress and assign more (or less resources as appropriate). Or, some other similarly pragmatic approach.

Standard deviation isn't something we've talked about before and I think it would be worth keeping this back for a specific post. (That's the point on 6 Sigma / 1 Sigma above). What I think I will do for the remainder of this post is focus on point 5 above.

There are undoubtedly a great many opportunities for the activity of forecasting to fail. I'm going to describe a few ways that (I've seen) project delivery deviate wildly from the forecast and then highlight some stratagems to help avoid it doing so.

Shoddy project planning - I don't know how many more project plans I'm going to have to work with that comprise 1000+ lines, rely wholly on duration based (rather than effort based) planning and (to top it all) incorporate 50%+ of hard coded dates.

I don't have the knowledge, capacity or inclination to write at any length on the topic of project planning and good practice using MS Project (or other). However, allow me to suggest that the inputs to creating a project plan include the following;
  • Experienced planners who understand critical path analysis, activity on node / on arrow techniques
  • Knowledgeable staff who have either been through a structured programme of learning or other activity necessary to equip them with the knowledge needed
And some general useful pointers while we're on the topic

  1. The near term should be at a far greater level of detail than than the mid- or long term
  2. Decompose tasks to an 'appropriate' level of detail
  3. You don't have to, but project plans comprising tasks which track back to product break down structures and product descriptions tend to have a much firmer foundation
  4. Supplement your forecasting with appropriate controls so that if you're wandering off schedule, your have good information early
  5. Make sure public holidays and staff leave are configured within your resource planning
  6. Agree up front what the resource capacity is (70%-90% - typically 80%). Never 100%.
  7. Practice rigorous change control. You may (or may not) be able absorb additional tasks of less than 0.25 days effort. Make sure you have a mechanism to manage anything that exceeds what you can comfortably accommodate.
  8. Building (clandestine) budget contingency into business cases and budget forecasts is wrong (and can be fraudulent). However, I'm pragmatically fairly well disposed to building in a degree of flexibility / contingency into forecast schedules. You'll be able to cope with a greater degree of unforeseen events and I've yet to find a client who complains when you bring something in a bit early. You'll also be able to give the client an answer other than no when he asks if you can bring something in a bit quicker.
Supplier management issues certainly figure highly in my short list of frustrations most likely to unhinge a project plan. You're embarked upon a project and chances are, so is your supplier with all the vicissitudes to which projects in general or prone. Some points intended to enhance stability follow.

  1. Don't blur the lines between dependencies. If you have a dependency for which the supplier is responsible, don't start to re-plan and re-forecast (unless absolutely necessary) when the supplier starts to slip. That's a recipe from a problem shared is a problem doubled.
  2. Make sure your contract and commercials with the supplier are appropriate
  3. Make sure you have the appropriate written and agreed documentation to support the supplier's statement of work and scope of supply. 
  4. Verify your supplier has instated 'good practice'.
Governance or lack thereof. Get the right decision made, at the right time to the right criteria. Incidentally, it's worth mentioning IT Governance in here - this is distinct to the typical corporate and project governance insofar as it's principal objectives are maximising value and minimising risk. Technical design assurance, testing, change management and a solid approach to service transition all comprise elements of good IT governance.

A little more yet to cover on this topic generally. If I'm feeling suitably whimsical, I may relay at some future point my thoughts on the role of analogue computing to forecasting in project management (another first for PMfizz surely?)












Saturday, February 9, 2013

Equine allegories

First, please excuse the title  - a cunning attempt at promoting my blog. Anyone (and I mean anyone) who Googles "Equine allegories" is sure to be directed straight here. A winning strategy I think you'll agree.

Now, for those of you not in 'my manor' as it were, there's been a bit of a scandal of late with beef not being beef. Suffice it to say, jokes about Red Rum Steak abound. 

I think this has got some fascinating insights for anyone in the business of change.

Let's talk about quality assurance and product acceptance first. Projects are comfortable in a landscape of customer / supplier. Other approaches exist. I've always adopted a stance that the supplier is accountable for quality assurance. Equally, the customer never divests themselves of the onus for due diligence corresponding to product acceptance. It is too risky to rely wholly upon the supplier's quality assurance.

Now, risk. I've never been comfortable about the whole 'transferral' of risk thing. Mainly, because I don't think you can transfer risk predictably and reliably. I'm minded of a supplier who was responsible for building the new Wembley Stadium and F.A cup finals which were held in Cardiff (Wales) for 2 (3?) years due to delays in construction. And similarly here, while the supermarkets in Britain can point the finger at their suppliers, the fact they've not done their own testing isn't going to sit well with their customers. Particularly when they've almost certainly profited from the whole fiasco..

From a consumer point of view, it seems to me that the consumer demands choice at the lowest  price. Now hold on a minute there, because actually, I don't.. But, it's the line spouted by the business's involved in grocery retail so there may be a grain of truth in it. So, if we only make a purchasing decision predicated upon cost, then we're likely to get a supplying decision predicated wholly around cost with all the consequences it brings.

You'd think governance would play the part of fair, honest and effective broker in all this. I wouldn't. Basel II, Sarbanes Oxley and FSA couldn't avert the biggest banking crisis of a generation. You can try all the tricks in the book to minimise risk, maximise value and ensure the right decisions are made by the right people to the right criteria at the right time. But, if greed, gain and guile are the prevailing cultural themes within an organisation, it won't matter.

But, there is an up. Discovering that stuff has gone wrong today makes you better off than you were yesterday. You can start the job of corrective action, you can learn some lessons and strengthen whatever is needed to prevent re-occurrence. 

Finally, there's something else to take away from all of this. We can read and write all the books we like. Develop the discipline of project management in new and exciting directions. Effective and sound judgement however is something ephemeral, acquired slowly and lost quickly. 


Saturday, February 2, 2013

Requirements part 5 - a very useful spreadsheet

I think there might actually have been one or two more posts on requirements than 5. No matter the end of the tunnel is in sight.

I've written quite a bit about what not to do with requirements and conversely some useful salves for common problems. What I haven't done (until today) is state clearly my approach to managing requirements (and more besides) or provide the tool to get the job done.

To date, we've talked about MoSCoW analysis (yuk!), pair-wise comparison, cost of compliance / non-compliance, KANO analysis and quite a bit more besides. We've never talked about UML or a bunch of other stuff, but ultimately (as you'll see) that might not matter too much.

Consider the illustration below - a veritable soup of inputs relating to requirements. Equally, a customisable and completely transparent score card that can be constructed and agreed by stakeholders early in the process.

What we're starting to get towards here is an approach to requirements prioritisation and management that can be highly customised to suit any situation. 

Get the stakeholder buy-in right, get the score card right and the rest will follow.

In the example below, I've used the following scoring elements - you however can use what you like.


  • MoSCow - exactly what it says on the tin. MoSCow does have its place albeit do remain cognisant of the limitations previously discussed.
  • Kano - see last post. A quick and easy way of assessing non-monetary value
  • Contribution to the business plan - if it doesn't contribute, should you be doing it?
  • Compliance - do we have to have this to meet regulatory requirements?
  • Senior stakeholder flag - if the the budget holder wants it in taupe, then let's have that right out in the open from the get go.



Your score card might incorporate the elements illustrated above or be something complete different. You might have specific organisational imperatives which mean you incorporate none of the elements above - fine. The approach is no less valid.

So - you've got a score card - what next? Excel that's what. What you're seeing below is the scorecard above incorporated into Excel.


It's not too busy a spreadsheet but it has got a couple of tricks up its sleeve.

First, the fields are 'constrained' and aligned with the scorecard.











And, we've got a a simple but long formula to do the scoring calculation. Note the red highlight. We don't put the scoring in the formula itself - we use a lookup to a table elsewhere. This is important and we'll discuss this more later.

=IF(C2="Must have",Lookups!$B$1,(IF(C2="Should have",Lookups!$B$2,(IF(C2="Could have",Lookups!$B$3,(IF(C2="Won't have",Lookups!$B$4)))))))+IF(D2="Dis-satisfier",Lookups!$D$1,(IF(D2="Satisfier",Lookups!$D$2,(IF(D2="Delighter",Lookups!$D$3)))))+IF(E2="Key",Lookups!$F$1,(IF(E2="Required",Lookups!$F$2,(IF(E2="Aligned",Lookups!$F$3)))))+IF(F2="Yes",Lookups!$H$1,(IF(F2="No",Lookups!$H$2)))+(IF(G2="Yes",Lookups!$J$1,(IF(G2="No",Lookups!$J$2))))

I've uploaded the spread sheet here and you can play to your heart's content.

Some things to bear in mind.


  1. You aren't constrained to 'sum' the scores. Multiplication has its place particularly as it opens up using a zero to effective nullify a requirement
  2. You aren't constrained to using this just for requirements - the same approach works very well for (say) assigning a risk rating to server moves in a data centre migration
  3. I've used significantly larger spreads sheets both in terms of the number of criteria used and the scores which correspond to those criteria. Undoubtedly there's a limit but I haven't found it. If you do (and good luck with that) you can always split the formula in two and sum the output.
  4. Don't limit yourself to linear scoring - in point of fact, you're going to need to justify very carefully the use of linear scoring (i.e 1,2,3,4,5,6 as opposed to 1,3,8,20). Most things (I think) will benefit from a non-linear scoring approach.
  5. Make sure you get your criteria right from the get go, the scoring only needs to be 'about' right as we re-tune that later on.
  6. Weighting - don't think you can't apply a specific weighting to one or more elements on the scorecard - in point of fact this is just another way of playing with the scoring but don't rule it out.
  7. If you're smart enough you can probably use a custom list in SharePoint to do this.
Finally, getting the scoring in the scorecard right from the get go is tough. So tough in fact that I discourage you from trying. Stakeholders can get a bit cagey too as, while they see the merit in the approach, they tend to be less certain about getting tied down by a scorecard that they (quite understandably) can't appreciate the fullest implications of at the outset.

Fine tuning the scoring is the subject of the next post.




Monday, August 13, 2012

Projects? Like poker? Surely you jest...?

If you've been around a project life-cycle a few times, you've probably stood on the periphery of some passable projects, some not so good projects, the odd biblical disaster and possibly, just possibly a success story or two.

I've often reflected on the various circumstances corresponding to success and failure and have (as doubtless we all do) a few thoughts on the matter. 

However, let's look elsewhere for inspiration other than our own personal project hurt lockers for a moment.

How do Google and Apple manage such consistent successes? What are their project manage approaches that so consistently deliver commercial success in amongst the most high risk, cut throat fields imaginable?

Well here's the thing - Google and Apple fail just as much (if not a good deal more) than us mere mortals.

So the distinction is certainly not simply one of success or failure.

I'm not going to prattle on too much at this juncture as most of this is done to death elsewhere in great detail. I can't help however draw a distinction between projects and poker however. Namely, when you lose, try and lose a little. When you win, try and win a lot.

You don't read a lot in the project management blogosphere about Prince 2 - admittedly, it can be a dryish cornerstone of what must seem to PMI / PMBOK advocates to be a project management oddity. I would even have a modicum of sympathy for the view that it is a project management methodology with no project management due to its conspicuous (and quite deliberate omission) of earned value management or anything resembling it. 

But, I will break the trend a little in the context of this post (possibly a web first to encompass poker and Prince 2 within a single blog post).

I had to put pen to paper in a professional setting recently and wrote the following. 

"Teams seeking to undertake projects via Prince 2 are challenged by constraints which often diminish the effectiveness of the Prince 2 methodology and consequently the overall success of their projects. These constraints relate to people, processes and systems. Specifically, the efforts to recruit appropriate staff, acquire Prince 2 knowledge, develop and implement appropriate policies and the subsequent execution of the Prince 2 methodology is exceptionally demanding."

And, I know what I'm talking about here having assembled a the odd 180 line responsibility assignment matrix for the purposes of administering the full suite of Prince 2 processes. And, yes, just in case you were in any doubt, that's 180 activities that that need to be undertaken in a fully compliant (admittedly non-tailored) Prince 2 compliant project that are quite independent of actually delivering anything. I'll upload this matrix to the resources page accompanying this blog in due course.

But, I remain a fan albeit with one or two provisos. Consider the following.


  1. Continued business justification
  2. Learn from experience
  3. Defined roles and responsibilities
  4. Manage by stages
  5. Manage by exception
  6. Focus on products
Not too shabby a list of tenets for the project manager to abide by is it? Well those six points are 6 of the 7 Prince 2 principles. The seventh is "Tailor to suit the project environment" which goes some way to palliating the 180 line items in the responsibility assignment matrix.

Just in case some of you were sitting there scratching around a long ago Prince 2 practitioner course thinking you really don't recall anything about 7 principles (and seven additional themes for that matter) you're probably right. I'm not sure what preceded Prince 2 2005, but in 2009 the framework was overhauled with the imaginative re-branding of "Prince 2 2009". I judge it to be substantially improved.

And what's all this got to do with Apple and Google? Well, whatever those folks are doing with their project management methodologies I'm pretty sure it will incorporate the 6 principles above. I shall resist the urge to conclude that Apple and Google are Prince 2 houses but I am guessing they don't rely much on full-houses either.












Wednesday, July 18, 2012

Making life easier (and a bit of process stuff)

Projects generally have a lot of 'interconnectedness'. And please - I don't just mean railway projects.

Processs are rarely 'stand-alone'. The outputs from one process are, more often than not, the inputs fir something else. (So help me) you'll start to hear the words ecosystem and (abandon hope all who enter) 'synergy'.

In an ideal (and possible mythical world) you have ERP, CRM and EPM tools into which all your various risks, issues etc are included. But, from time to time, the enterprising PM may find themselves without these tools and forced to fall back on more prosaic mechanisms (by which I mean Excel).

I've provided a spread sheet here. I call it ACRID (derived from Assumptions, Constraints, Risks, Issues and Dependencies). You'll also come across the term RAID (minus the constraints), and you'll probably not often come across a CORDIAL log which (of course) contains the lessons learned log. Any attempt to include a quality log is headed for the rocks.

We don't want to make life too hard for ourselves and, of course, we'll want to keep an eye on the whole process ecosystem angle so we're not duplicating effort left, right and centre.

I include here a template for a highlight report. I like highlight reports as I know of no better way to bridge the divide between the poets (for whom business transformation is a mere pen stroke) and the plumbers who lie awake all night worrying about it. I take some license but there's a sliding scale in there somewhere.

So, back to the whole inputs and outputs thing. If you take a look at the highlight report template (which is aligned with Prince 2) you'll notice there's quite a bit on work packages and products. Check back to previous posts and you'll have all all you need to cut and paste into the highlight report.

In fact I'll paste in the contents page from the highlight report template and append it with where you derive the content from each section from.

1. This reporting period

Not much going on in here

1.1 Work Packages

...Or here

1.1.1 Pending authorisation

If you need them, you'll have been writing them and you'll know which ones are outstanding authorisation

1.1.2 Completed in this period

From the project plan, paste in relevant sections of WBS

1.2 Products completed in this period

From the project plan, paste in relevant sections of WBS

1.3 Products planned but not started

From the project plan, paste in relevant sections of WBS


1.4 Corrective actions taken during the period


Issue log or other sources as appropriate

2 Next reporting period


Not much going on in here



2.1 Work Packages

...Or here



2.1.1 To be authorised

From the project plan, paste in relevant sections of WBS

 2.1.2 To be completed in the next period

From the project plan, paste in relevant sections of WBS


2.2 Products to be completed in the next period

From the project plan, paste in relevant sections of WBS

2.3 Corrective actions to be completed in the next period


Could be anything - use your judgement to include what you feel is appropriate


3 Product and stage tolerance status

SPI / CPI figures as appropriate (this will have to wait for another day for detailed coverage).


4 Requests for change


From the ACRID log so long as you raise all your changes as issues


5 Key Risks


From the ACRID log

6 Issues

From the ACRID log

7 Lessons Report


From the ACRID log

***************************************

Some points to bear in mind.
  1. Truncate (i.e. hide a few columns) on the product descriptions, WBS elements, risks etc as you'll not fit them all on a single landscape A4 and the detail is probably more than your audience will want
  2. I'll cover off a bit on the cost performance index (CPI) and schedule performance index (SPI) another day.
  3. Corrective action could mean almost anything - include what you think is appropriate
  4. Some stakeholders will want detailed information about resource burn, budget status or other detailed information not included above - this is a good sign and shows that the sponsor is 'on board' and giving the project focus.
And, to wrap up the topic of the highlight report I conlude with the following key points which I hope will impress upon you the benefit of producing it, even if your stakeholders are sanguine on the topic.
  • It is an excellent tool of communication to all stakeholders, both to relay issues and status concerns but also to keep all parties abreast of progress. It is a principal tool by which the project manager can relay, escalate and communicate issues and anxieties which require board / sponsor input.
  • I find it amongst the best ways of structuring a project board meeting, particularly for stakeholders less experienced in sitting on project boards
  • If (like me) you keep all your WBS elements, product descriptions and logs up to date, with practice, you can produce one of these in about 20 minutes.

Wednesday, June 27, 2012

Sewing up a few lose ends and knitting it all together

Time to wrap up (for now at least) on the WBS and allied products.


I mentioned that sometimes there was a lot of work and not much product. If you need better control around this or simply better control period then I enclose a work package template here.


The first half is pretty much Prince 2 all the way. The second half incorporates specific test management activities intended to root out defects.


Two interesting points about work packages - sometimes resource pools really respond well to them. They can definitely accelerate delivery. Secondly, if you ask for written checkpoint reports from assigned resources you can rely on finding out problems after they've happened. If you take the time to verbally engage with the assigned resources you might be lucky to catch sight of problems before they occur.


Next I include a small but useful resource which is distilled from the WBS (which we have talked about) and the project plan (which we haven't) which nicely sows up all the delivery dates for all the products. 


For ease of administration I recommend including the WBS dictionary, the product descriptions and the product handover log on different work sheets in the same work book. I've never done anything clever with this using SharePoint / Excel Web Services but doubtless they'd be some value in exploring this.


I'm a bit cautious with the illustration below but felt it was worth including even in its slightly flawed state. The PBS is a bit nomadic, and there are one or two abstractions too far. But I think there's more right with it than wrong so I include it here and welcome suggestions for how it can be neatened up a bit.


There's a heck of a lot more worth exploring, both central to the illustration above (testing, estimating, tracking and controlling progress) and peripheral (benefits management, value management, business case writing) to name but a few. But, that's all for another post on another day.



Saturday, June 23, 2012

Taking the WBS forward towards a project plan

In my last post, I talked at some length about the work breakdown structure as a foundation for all that was to follow. I summarised some points worth noting when creating and manipulating work breakdown structures. One of the limitations of a WBS is that it can't incorporate that much detail. And for some of the WBS elements, you're going to want a lot of detail.

I'll come on to how much detail and for what purpose shortly. In the meantime, l include the following table which supplements the WBS elements with more detail and specifies the product descriptions which correspond to any given WBS element.


Most of the fields are self explanatory and most come from Prince 2. There are things which Prince does very well - this is one of them.


One or two things aren't self-explanatory. BCWS stands for budgeted cost of work scheduled and this is beyond the scope of this post. It's a component of earned value management for those sufficiently interested. The CAM is the Control Account Manager and while this terminology is fairly specific to aspects of earned value management, you'll discern that this is the person(s) who is accountable for the product's delivery and ensuring it meets requirements.


All the WBS elements should incorporate version control. The related products descriptions relate to specific products that will be produced during the execution of this work. The nomenclature is deliberately 'transparent' and it should be readily apparent from any product reference what the corresponding WBS element is. The schema of the product descriptions is larger and will be the subject of a subsequent post. You should note that if the WBS element doesn't output a product, there won't be a product description and this might be as far as you elaborate.


You can download the specimen template shown above here

The start and finish dates are fed back into the WBS dictionary when you've completed the scheduling work in the project plan.


A few points on the subject of detail and how to assess how much of it you need to have.

  1. Is your project intolerant around costs? Schedule? Quality? All three? This should inform the level of detail where appropriate
  2. Is the work novel or contentious. Has reference to corporate or programme lessons learned resource indicated anything about which you should be wary?
  3. Are you expecting lots of change around the specific element of the WBS or resulting products?
  4. Is product acceptance a particular concern?
  5. Is this a new supplier or one with whom there is little prior precedent?
That's a few points to be considering when assessing the degree of detail that should correspond to a particular WBS element or its related product descriptions. 

Incidentally, at this point I've still not covered where a really helpful narrative can (and should) be included. In my last post, I included an illustration of the WBS. When publishing the WBS, I always include an accompanying table with some supporting information about what a specific element of the WBS actually encompasses.

I include an illustration below of what I usually include with the WBS.



And you can download the template here


I'll deal with the product descriptions next and then we'll be in the business of assembling our project plan.